一、价格调整(变化):看FIDIC规定如下
any amounts to be added and deducted for changes in legislation and
changes in cost, in accordance with Sub-Clause 13.7 [Adjustments for
Changes in Legislation] and Sub-Clause 13.8 [Adjustments for
Changes in Cost];
按照第13.7 款[因法律改变的调整]和第13.8 款[因成本改变的调整]的规
定,由于法律改变和成本改变,应增减的任何款额;
二、变更的金额:
(a )the estimated contract value of the Works executed and the
Contractor’s Documents produced up to the end of the month
(including Variations but excluding items described in sub-paragraphs
(b) to (f) below);
截至月末已实施的工程和已提出的承包商文件的估算合同价值(包括各
项变更,但不包括以下(b)至(f)项所列项目);